MT Nusa Sumatera - Ship Building under Magsaysay Shipping Inc., Full Electrical and Automation of
new building of a 5 million liter tanker ship.
MT Mactan Island - Implemented SCADA on Engine Safety System, Installation of pressure monitoring.
Cargo Tanks Monitoring Automation:
MV General Romulo: Implemented PLC control for Engine Monitoring System.
MV General Evangelista - Implemented Pneumatic control for ballasting.


Building Management Systems and SCADA Power Monitoring Projects
Current * Polaris Project - BMS, SCADA and Auxillaries; Aeon Land Dev. Corp.
SM Mall Masinag
ABS-CBN TV Station - BMS and SCADA Power Substation Monitoring
ELJ Building - BMS System
Bangui (Ilocos Norte) - Northwind Power - Wind Turbine interface to SCADA
A Place Building - BMS System
Henry Sy Sr. Hall - De La Salle University - BMS System
SM 2-ECOM Center - Centralized Power Metering System
SM Olongapo - SCADA Power Substation Monitoring
SM Mega Mall Extention - Substation SCADA monitoring
SM Cyberzone 2 - Substation SCADA monitoring

Power System Design and Analysis Projects
150MW Burgos (Ilocos Norte) Windfarm
Nestle Philippines Factory

PMFTC Marikina Factory
ICTSI Substation
Team Energy Philippines Power Station
SUNPOWER Manufacturing Plant
Medical City (Ortigas, Pasig City) Grounding System Assessment (podium, nursing tower one and two)

Electrical Installations, Testing and Commissioning Projects
The Medical City (Ortigas, Pasig City)
Preventative Maintenance and Repair of 4 Units 400KVAR Capacitor

Preventative Maintenance of Sewage Treatment Plant (Rewiring and Simulation of Automatic Operation)
Philsaga Mining Corporation (Bayugan II, Agusan Del Sur)

Scope of Work: Testing & Commissioning
Equipment: Complete 10MVA 69/13.2Kv Power Substation, 3 x 2MW, 4.16Kv Synchronizing Panel (Mill Site),
3 x 2MW, 480V Synchronizing Panel (Mine Site)                            

SOCOTECO 2 Cooperative (General Santos City)
Scope of Work: Testing & Commissioning  
Equipment: Complete 20MVA 69/13.2Kv Power Substation                                 

Zamsureco II Cooperative (Zamboanga Del Sur)
Scope of Work: Testing & Commissioning
Equipment: Complete 20MVA 69/13.2Kv Power Substation (Ipil), Complete 10MVA 69/13.2Kv Power Substation (Danda)        
Carmen Copper Corporation (Toledo City, Cebu)
Scope of Work: Design, Wiring, Testing & Commissioning
Equipment: Retrofitting of 7 units, 3000Hp Ball Mill Controller Interfaced with Yokogawa DCS, Retrofitting of
Protection Relays  Substation, Retrofitting of 34.5Kv Substations, Supply of 3.3Kv Switchgears                                                            

Gaisano Mall (Iligan City)
Scope of Work: Testing & Commissioning
Equipment: Complete 5MVA 69/13.2Kv Power Substation                                

Eton Centris Cyberpod (Quezon City)
Scope of Work: Testing & Commissioning
Equipment: 3 x 1.25MW, 400V Synchronizing Panel with HMI monitoring      

Eton Centris Walk (Quezon City)
Scope of Work: Testing & Commissioning
Equipment: 400V Low Voltage Switchgears and Panel Boards                          

E-Block 2 Tower (I.T. Park, Cebu City)
Scope of Work: Testing & Commissioning
Equipment: 3 x 1.25MW, 400V Synchronizing Panel with HMI monitoring      

Noreco II Cooperative (Pulantubig, Dumaguete City)
Scope of Work: Testing & Commissioning
Equipment: Complete 20MVA 69/13.2Kv Power Substation                             

Iloilo Doctor’s Hospital (Molo, Iloilo City)
Scope of Work: Testing & Commissioning
Equipment: 2 x 800KW, 230V Synchronizing Panel                                           

Central Azucarera de San Antonio (Passi City, Iloilo)
Scope of Work: Testing & Commissioning 
Equipment: 20MVA, 69/4.16Kv Co-Generation Power Plant                             

Lee Plaza (Dipolog City)
Scope of Work: Design, Wiring, Testing & Commissioning
Equipment: 3 x 800Kw Synchronizing Panel with HMI monitoring, Complete 3MVA 13.2/480V Substation,
Low Voltage Switchgears                                                                  

SM 2-Ecom (SM Mall of Asia, Pasay City)
Scope of Work: Design, Wiring, Testing & Commissioning Design, Wiring, Testing & Commissioning
Equipment: Complete 4 x 2.5MVA 34.5/400V Substation,  Low Voltage Switchgears, Bus Duct Interconnections                                                                
SM City San Pablo
Scope of Work: Design, Wiring, Testing & Commissioning
Equipment: 50 units Variable Frequency Drives Controllers for AHU, Motor Controllers                                                                              
SM City General Santos
Scope of Work: Design, Wiring, Testing & Commissioning
Equipment: Complete 4 x 2.5MVA 34.5/400V Substation,, Low Voltage Switchgears                                                                 
United Pulp Paper Corporation (Calumpit, Bulacan)
Scope of Work: Design, Wiring, Testing & Commissioning

Equipment: Mentor II DC drives, Motor Controllers                                                                              

Eagle Cement Corporation (Bulacan)-5MVA Substation (turn-key project)
Rich Steel Corporation (Valenzuela) - Mentor II DC Drives
Casecnan Power Plant (Pantabangan, Nueva Ecija) - Commissioning of Static Exciter for 100MVA Hydro Power Plant

Petron Refinery RMP-2 Project (Limay, Bataan) - Equipment Testing for Siemens
NSX Gas Insulated Switchgear, Assembly of 2 x 45MVA & 2 x 15 MVA Shihlin Electric Power Transfer